For the team today was the day it really began to sink in the launch was getting close.
The satellite with the PLA attached was moved and mated onto the PAF. It looked really impressive.
![](https://earthcare8.earth/wp-content/uploads/2024/05/image-3.png?w=289)
![](https://earthcare8.earth/wp-content/uploads/2024/05/p5160069.jpg)
At the launch pad gas samples were taken of the purging lines for cleanliness analysis.
In the LLC the team had a walk through of the countdown procedure which really focused the mind. The satellite was then powered on to check all the connections through the PLA and PAF ready for tomorrows test.
Finally in the adjacent cleanroom the two fairing halves had arrived and were being inspected and prepared.
The propulsion team were finalising the decontamination in the adjacent facility.
![](https://earthcare8.earth/wp-content/uploads/2024/05/p5160008.jpg)
Then an early night as Dress Rehearsal tomorrow!!